August Update:

http://www.calgary.ca/Transportation...il-Tunnel.aspx

34/50 complete. At their current pace, the concrete pours for the tunnel should be complete in early October sometime.

http://www.calgary.ca/Transportation...August2012.pdf

Last edited by You Need a Thneed; 08-03-2012 at 06:57 PM.
You Need a Thneed is online now   Reply With Quote
Old 08-03-2012, 06:55 PM   #562
Table 5
Franchise Player
 
Table 5's Avatar
 
Join Date: Oct 2001
Location: NYYC
Exp:
Default

Every time this thread pops up, I think the tunnel has again been rejecte-oh wait, it's approved!!
Table 5 is offline   Reply With Quote
The Following 5 Users Say Thank You to Table 5 For This Useful Post:
Old 08-03-2012, 07:47 PM   #563
GreatWhiteEbola
First Line Centre
 
GreatWhiteEbola's Avatar
 
Join Date: Aug 2006
Location: Calgary, Alberta
Exp:
Default

I really hope they don't have a noise monitor in this tunnel...

__________________


Last edited by GreatWhiteEbola; 08-03-2012 at 08:00 PM.
GreatWhiteEbola is offline   Reply With Quote
Old 09-05-2012, 03:47 PM   #564
Bigtime
Franchise Player
 
Bigtime's Avatar
 
Join Date: Apr 2008
Location: Calgary
Exp:
Default

Today the city handed over the section of the tunnel underneath the runway so construction can begin above. On time and on budget so far:

http://blog.calgarymayor.ca/2012/09/...on-budget.html



Bigtime is offline   Reply With Quote
The Following 6 Users Say Thank You to Bigtime For This Useful Post:
Old 09-05-2012, 03:51 PM   #565
Table 5
Franchise Player
 
Table 5's Avatar
 
Join Date: Oct 2001
Location: NYYC
Exp:
Default

Man, that's pretty cool looking. As GWE suggested, this thing is going to be awesome for engine revs. Maybe it's time we started petitioning for a Calgary GP. Monaco on the Prairies.
Table 5 is offline   Reply With Quote
The Following 4 Users Say Thank You to Table 5 For This Useful Post:
Old 09-05-2012, 03:59 PM   #566
You Need a Thneed
Voted for Kodos
 
You Need a Thneed's Avatar
 
Join Date: Dec 2007
Exp:
Default

For those to lazy to count that's 41/50 sections complete. They have been averaging completing about 8 sections a month.
You Need a Thneed is online now   Reply With Quote
Old 09-05-2012, 05:24 PM   #567
You Need a Thneed
Voted for Kodos
 
You Need a Thneed's Avatar
 
Join Date: Dec 2007
Exp:
Default

More pictures (and higher resolution) from Calgarycitynews:



You Need a Thneed is online now   Reply With Quote
The Following 7 Users Say Thank You to You Need a Thneed For This Useful Post:
Old 09-05-2012, 05:53 PM   #568
TurnedTheCorner
Lifetime Suspension
 
TurnedTheCorner's Avatar
 
Join Date: Nov 2003
Exp:
Default

That sure is a tunnel.
TurnedTheCorner is offline   Reply With Quote
Old 09-05-2012, 05:58 PM   #569
stampsx2
First Line Centre
 
stampsx2's Avatar
 
Join Date: Aug 2009
Location: Calgary
Exp:
Default

How disappointing. That looks like it's only wide enough for a single lane in each direction. That will be one major bottleneck in the morning.
stampsx2 is offline   Reply With Quote
Old 09-05-2012, 06:04 PM   #570
morgin
Scoring Winger
 
Join Date: Mar 2009
Exp:
Default

Quote:
Originally Posted by stampsx2 View Post
How disappointing. That looks like it's only wide enough for a single lane in each direction. That will be one major bottleneck in the morning.
I'm not sure how you determined that the 6 lane tunnel can only hold 2 lanes, but.. ok?
morgin is offline   Reply With Quote
The Following 3 Users Say Thank You to morgin For This Useful Post:
Old 09-05-2012, 06:04 PM   #571
Barnes
Franchise Player
 
Barnes's Avatar
 
Join Date: Aug 2005
Location: Violating Copyrights
Exp:
Default

Quote:
Originally Posted by stampsx2 View Post
How disappointing. That looks like it's only wide enough for a single lane in each direction. That will be one major bottleneck in the morning.
That's only on direction. There's room for 3 lanes each way.
Barnes is offline   Reply With Quote
The Following User Says Thank You to Barnes For This Useful Post:
Old 09-05-2012, 06:05 PM   #572
Bigtime
Franchise Player
 
Bigtime's Avatar
 
Join Date: Apr 2008
Location: Calgary
Exp:
Default

Quote:
Originally Posted by stampsx2 View Post
How disappointing. That looks like it's only wide enough for a single lane in each direction. That will be one major bottleneck in the morning.
From the link I posted:

Quote:
The 620-metre long tunnel structure is being constructed to accommodate six lanes of traffic, with the provision for a future transitway,
Edit: Beaten twice!

Last edited by Bigtime; 09-05-2012 at 06:08 PM.
Bigtime is offline   Reply With Quote
The Following User Says Thank You to Bigtime For This Useful Post:
Old 09-05-2012, 06:13 PM   #573
stampsx2
First Line Centre
 
stampsx2's Avatar
 
Join Date: Aug 2009
Location: Calgary
Exp:
Default

Quote:
Originally Posted by Barnes View Post
That's only on direction. There's room for 3 lanes each way.
I stand corrected. In that case.....wow, nice job city planners.
stampsx2 is offline   Reply With Quote
Old 09-05-2012, 07:45 PM   #574
SebC
tromboner
 
SebC's Avatar
 
Join Date: Mar 2006
Location: where the lattes are
Exp:
Default

Quote:
Originally Posted by stampsx2 View Post
How disappointing. That looks like it's only wide enough for a single lane in each direction. That will be one major bottleneck in the morning.
If you think 1 lane each way would be a bottleneck, imagine no lanes each way! #SuckItBobHawkesworth
SebC is offline   Reply With Quote
The Following 5 Users Say Thank You to SebC For This Useful Post:
Old 09-05-2012, 07:49 PM   #575
FlameOn
Franchise Player
 
FlameOn's Avatar
 
Join Date: Oct 2010
Location: Calgary
Exp:
Default

Could someone remind me again what this "future transitway" will be? Is it the proposed LRT line?
FlameOn is offline   Reply With Quote
Old 09-05-2012, 07:55 PM   #576
BlackArcher101
Such a pretty girl!
 
BlackArcher101's Avatar
 
Join Date: Jan 2004
Location: Calgary
Exp:
Default

Quote:
Originally Posted by FlameOn View Post
Could someone remind me again what this "future transitway" will be? Is it the proposed LRT line?
Ultimately yes, but it will be done in stages. Summarized in this document showing the cross section of the tunnel: http://www.calgary.ca/Transportation...on-Oct2011.pdf
__________________
BlackArcher101 is offline   Reply With Quote
The Following User Says Thank You to BlackArcher101 For This Useful Post:
Old 09-05-2012, 08:31 PM   #577
Bunk
Franchise Player
 
Bunk's Avatar
 
Join Date: Jul 2006
Exp:
Default

Quote:
Originally Posted by stampsx2 View Post
I stand corrected. In that case.....wow, nice job city planners.
You mean nice job Mayor Nenshi. Quite simply, the project wouldn't have happened without him.
__________________
Trust the snake.
Bunk is offline   Reply With Quote
The Following 3 Users Say Thank You to Bunk For This Useful Post:
Old 09-05-2012, 08:34 PM   #578
Bunk
Franchise Player
 
Bunk's Avatar
 
Join Date: Jul 2006
Exp:
Default

Quote:
Originally Posted by FlameOn View Post
Could someone remind me again what this "future transitway" will be? Is it the proposed LRT line?
There'll be buses at first, but will move to rail at some point. There potentially could be a rail link between the NELRT and future NCLRT with a stop at the airport in the middle. LRT, or perhaps some sort of automated rail like SkyTrain.
__________________
Trust the snake.
Bunk is offline   Reply With Quote
The Following User Says Thank You to Bunk For This Useful Post:
Old 09-05-2012, 08:37 PM   #579
Table 5
Franchise Player
 
Table 5's Avatar
 
Join Date: Oct 2001
Location: NYYC
Exp:
Default

Quote:
Originally Posted by BlackArcher101 View Post
Ultimately yes, but it will be done in stages. Summarized in this document showing the cross section of the tunnel: http://www.calgary.ca/Transportation...on-Oct2011.pdf
Looking at that PDF, it seems like they could make it 4-lane each way if the desire was there. Although I propose we make it a Kramer-style single-lane comfort cruise, (and perhaps a ban on anything under a 6-cylinder and/or 250HP).
Table 5 is offline   Reply With Quote
Old 09-05-2012, 11:13 PM   #580
SebC
tromboner
 
SebC's Avatar
 
Join Date: Mar 2006
Location: where the lattes are
Exp:
Default

Quote:
Originally Posted by Bunk View Post
You mean nice job Mayor Nenshi. Quite simply, the project wouldn't have happened without him.
Let's not forget the voters and campaign team who helped get him into his position of authority.
SebC is offline   Reply With Quote
Reply


Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT -6. The time now is 05:05 PM.

Calgary Flames
2024-25




Powered by vBulletin® Version 3.8.4
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright Calgarypuck 2021 | See Our Privacy Policy