Quote:
Originally Posted by Wormius View Post
Now that I have had my phev for more than a year now, how difficult is it to add a couple of more panels and still be in Enmax’s good graces?
Very easy. If you have any above and beyond electricity usage compared to what the original system was sized for, you'd be able to revise the Microgeneration permit to account for that.

Ideally you have a micro inverter system, as its just a matter of getting the Microgeneration permit approved for expansion, and then adding additional panels/inverters without needed to do any work on the existing system.

You can only apply for one MG revision every 12 months, so if you've been installed over a year ago, you'd be ready to consider expansion.
the-rasta-masta is offline   Reply With Quote