I kept a detailed log of when things happened throughout the period from when I reached out to the loan being paid to me. Hope this helps for anyone thinking about solar. It's a long process that I was on top of at each step but there are many things in the background like permits, applications, etc. that just take a long time.

Code:
Requested Info - Feb 18
Sent House Info - Feb 21
SolarYYC Quote Received - Feb 25
	
Heat Pump Quote - Feb 26
Heat Pump Install - March 7
	
SolarYYC Contract Signed - Mar 17
	
1st Energy Assessment - Mar 21
Submitted to NRCAN - Mar 24
	
Greener Homes Loan Submitted - Mar 25
Loan Application Accepted - April 8
15% Received and Paid - April 18
	
Spot Power Pre-Solar Rate - Jul 16
Panel Swap - Jul 22
Spot Power Enrollment - Jul 24
	
Solar Install - Jul 29
Elec. Inspection- Jul 30
System Switched On - Jul 30
ENMAX Microgen Submitted - Jul 31
	
2nd Energy Audit - Aug 5
2nd Audit Report Received - Aug 8
	
Funding Requested - Aug 8
Funding Approved - Aug 11
	
ENMAX Microgen Commission - Aug 13
Spot Solar Club $0.0849/kWh - Aug 13
High Solar Rate $0.30/kWh	 - Aug 13
YYCSolar Invoice Paid	- Aug 14
	
Loan Deposited - Aug 15