I am, but why would you need the tile setter to do things like liquid membrane etc? I would think they would come in after everything is done up to the point where the tile needs to be installed. I would expect the drywall contractor to be doing the installation of the schluter material or whatever.
|
As puckedoff said, the tiler generally does that part. They're guaranteeing the tile work and the quality of the substrate is a huge part of the integrity of the tile job. Drywallers don't normally do anything but drywall. There may be situations where they'd install cement board in a wet area, but they wouldn't normally do the waterproofing or anything; that would be up to the tiler.