The UCP can only be blamed for around 13 months. Most of the delays have been self-inflicted.

Green Line timeline:

Late 2015: Construction to begin in 2018, opening in 2024 for the entire 40 km line (from Panorama to Seton)
May 2017: Cut back to 16th Ave - Shepard, construction to begin in 2020 and opening in 2026
June 2019: 4km core tunnel no longer feasible, new plan developed with construction expected to begin 2021, new managing director hired
June 2020: Council approves new plan with shorter tunnels and 3 phase Stage 1 but not approved by Alberta
Sept 2020: Managing director leaves
July 2021: Alberta approves new plan with 2 phase Stage 1, new CEO for GL is hired
April 2023: Constructor is selected but requires 16 months for design
June 2024: 60% design is finished
What a disaster of a project. I had assumed we were at 60% at least when they did the RFP?