Originally Posted by Fuzz
Noticing a distinct lack of designs for anything north of downtown. 
|
This is what it says on the website currently:
Phase 2
Phase 2 – Eau Claire to 16 Avenue N.
In June 2020 City Council approved the Stage 1 alignment from Shepard to 16 Avenue N. Following a review of Stage 1 of the project by the provincial government, the Green Line Board announced a revised procurement strategy to build the Green Line in two phases:
Phase 1: Shepard to Eau Claire
Phase 2: Eau Claire to 16 Avenue N.
A decision on building Phase 2 has not been made yet. The Green Line Board will make this decision once more is known about the costs and risks for completing Phase 1.