Per news conference:
- 3 pipe segments are in Calgary, 2 have been sourced from the USA and should be here mid next week.
- Survey crews locating those hot spots on the surface and doing surface surveys to allow for excavation plans, should be completed next couple of days
- the remaining 300m to be inspected still not yet complete due to more water remaining than expected
- looks like the 5 hotspots are between the current break and shaganappi pump station (this means along 16ave with easy access)
- still estimating 3-5 weeks
- overland temporary piping being investigated (from my experience, this would be difficult to maintain potable water rating while at the same time be quick)
- On question on who's accountable for this, a forensic report regarding the piping will be made available to the public when completed