Quote:
Originally Posted by AC
We have our SolarYYC install happening tomorrow after a surprise opening. Happy to move the install up a couple weeks.
I'm curious how long the remaining parts of the process take. City inspection, 2nd energy audit, and receiving the grant.
It's been pretty seamless so far other than needing to wait 6 months post new build possession.
|
Based on my experience:
-Inspection should be about a week.
-After the inspection is passed your installer will submit your microgen application to Enmax for approval and that could take 3 or 4 weeks depending on how backed up they are (it says it should take 10 days but that wasn't my case recently.)
-Depending on your auditor it might be about two weeks before they can do your post-retrofit evaluation. After that it could be a few weeks before they submit your paperwork to the Greener Home program portal (in my case it was almost 4 weeks and I had to hound them to get it submitted.)
-After that is submitted you can request your loan amount within a few days and payment will be about two weeks. The grant approval and payment will be about 8 weeks.
My install was around May 10. July 21 was the day that my loan was deposited. Yesterday was the day that my grant was finally approved and it says it could take up to 30 business days for the cheque to arrive but my buddy said it is much quicker than that.