Quote:
Originally Posted by Acey
They're paving the big new bridge over the river now, looks to me like it's ready soon.
I drove through there today for the first time in months, everything looks good to me. I see some places where they've learned from their mistakes on the ring road legs. We'll have to see annoying that EB-SB single-lane ramp is but I don't see it being significantly worse than the single-lane SB-WB ramp at Stoney NE/Deerfoot even though that one is downhill.
|
According to the latest WCRR project update email (June 26), once the bridge opens, the other one will be closed for rehab. Not sure for how long though.
Quote:
Waterproofing tile has been placed on the entire length of the bridge deck as the precursor to paving. Once paving and other finishing works are complete, traffic will be shifted to the new bridge and rehabilitation work on the existing bridge will begin.
|
http://secure.campaigner.com/csb/Pub...3z308-c09ranz0