Lots of good information from John Bean on yesterday's Flames Talk. It's a good listen so go seek the podcast (skip the Smith part) but here's some points.
  • Site increased from 7 acres to 10 acres thanks to Stampede land swap negotiations
  • All parties wanted a community arena in previous iteration but couldn't fit it in the 7 acres
  • Indoor gathering plaza will allow loading the building out of the elements
  • Outdoor plaza will act as Red Lot
  • "New" road and intersection on the SE of the Stampede grounds connecting to 25th
  • Lane reversal systems
  • Cost overruns on arena/community rink shared 50-50 with City & CSEC
  • Starting with $850 million a more realistic number than previous deal
  • Design will find opportunities to save on these numbers
  • Formal agreements starting Friday
  • Development manager to oversee entire construction needs to be hired
  • Design team and construction management team hired after development manager
  • 32-34 months of construction from break ground to building opening
  • 36-40 months +/- from now [woah! nah that's too quick for hiring/design/permits/procuring]
  • Some of the work already done should be able to transfer over