Presumably utility work or something? They'll probably come back and repave the whole thing at some point, the patches are probably temporary. But didn't they just redo all of 17th a couple years ago?
Unfortunately this is part of the same project. We are now in year five of the project. Sidewalk work scheduled for next year and the year after that.

It's one of the worst managed projects I've ever seen. My commute is a walk down 17th and the condition of the sidewalks is atrocious. It's awful for people with mobility issues.