Quote:
Originally Posted by burn_this_city View Post
Can't really fast track anything with supply issues. Most projects are 24-36 months depending on size for a straightforward debottleneck. Complicated equipment used to be 40-52 week delivery we now see 60 weeks. We also lack man-power on the technical side of things with 7 years of wave after wave of layoffs.
Yeah I've heard several anecdotal reports of companies having problems staffing up. I imagine a lot of experienced people left the industry over the last decade, so there is a vacuum in terms of knowledge and experience in some of the more hands-on areas. Offer enough money and people will come back...but that does take time...and money. In the meantime, while new recruits get up to speed, we probably should expect less efficiency, and a higher chance of error.