View Single Post
Old 02-01-2022, 03:43 PM   #1162
CarlLester
Crash and Bang Winger
 
Join Date: Apr 2013
Exp:
Default

Quote:
Originally Posted by you&me View Post
A builder we've been talking to lately is saying 8-9 months once permits are in place... This is for a custom build on a redevelopment lot. As far as delays, he says the actual construction isn't as much of an issue as some finnish materials, appliances, etc.
Can confirm. In the middle of a full reno right now. If all plays out without major hiccups, I am looking at 6-7 months to complete.

Longest lead items for us have been appliances (if current ETA date holds, it will be 9+ months from order date to delivery) and windows (if current ETA date holds it will be about 5 months from order date to delivery)
CarlLester is offline   Reply With Quote
The Following User Says Thank You to CarlLester For This Useful Post: