Quote:
Originally Posted by Lubicon View Post
Years ago when they were building the Stoney/Crowchild interchange the public updates they periodically provided subtly changed wording from 'progressing on time' to 'progressing on schedule' part way through the project. The project had fallen behind the original timeline significantly so they kept updating the schedule to reflect these delays and therefore cold continually claim the project was on schedule.
I seem to recall an interchange upgrade near my house that said "April to Aug 2018" or something. It didn't even start until Sept and didn't finish until the following summer.

What is even the point of these dates if they mean nothing?