Quote:
Originally Posted by GreatWhiteEbola
The presentation from the January 16th information session is available here
Complete Concept Design - June 2020
Complete Schematic Design - September 2020
|
Nice. From the presentation slides:
Milestone Date
Select Prime Design Consultant March 2020
Select Construction Manager March 2020
Complete Concept Design June 2020
Complete Schematic Design September 2020
Complete Design Development December 2020
Construction Start August 1 2021
Substantial Completion May 2024
Info should start coming fast and furious in 2020. Man, I did not think this year would actually come to fruition.