From what I can recall
1) The cities report infrastructure cost including many optional things.
2) The Flames claim they have a consultant tell them that if they re mediate the land incrementally while they develop the land build CalgaryNEXT it will cost $50 million
|
One of the things that Bean said at the STH event a couple of weeks ago was that the city report basically budgeted to do the same work twice. For the clean-up costs, it includes the costs of cleaning the soil and returning the site to bare ground for construction. Then, the construction costs include going from the bare ground.
In reality, you would never do it that way. You'd dig up the contaminated soil, then put the building right into the hole you've already dug.
That's one of the sources of savings he mentioned.