Means no such thing. I had asked her (and AB Trans) how much longer SB Deerfoot would be down to one lane for paving, as it caused massive delays all weekend. That was her response, and AB Trans also just replied and said:

Quote:
Thank you for contacting the Government of Alberta [...]

Our southeast Stoney Trail contractor has informed us that the paving activities on Deerfoot will continue for the rest of the week. In general a minimum of two lanes will remain open to the traffic on the main line but with the amount of work being done, it may cause some delays. [..]

Kamran Mirza, M Eng., P. Eng.
Urban Construction Engineer, Calgary
Alberta Transportation
Ph: (403) 801-3712