Do you think that they will have that overpass done in time for Fall 2013? All they really have done there is build the roadways towards Sundance Blvd
|
Red Deer piling has pulled up all of their gear and has gone onto their next contract and they still have 200 piles to drive. They were supposed to be finished by the 30th of July. But Chinook is not ready so they have moved on for now.
If we have another mild winter like we did last year I think they can get back on track but if we have a long wet winter they wont be done by next fall. It is hard to see but the do have a fair amount of the actual road work finished they just have to get approaches