Quote:
Originally Posted by CaptainCrunch
City pre-approved the fabricator company, and the expectation is the same on a fixed price contract, that the company is able to deliever non crappy work and live up to the contract
Granham will go after the city for the lost time, thats the way the contract works. The city will have the option to go after the vendor fabricator
|
Do you have a source for this? As I understand it, within a lump sum contract the general contractor (Graham) should be responsible for the work of the subcontractor (Augescon).