Originally Posted by First Lady
I seem to recall the welds that were at issue, were the ones done in Spain... I could be wrong though.
|
I could be wrong, but isn't the general contractor responsible for the subcontractor's work in this situation? The city pre-approved Augescon (the Spanish subcontractor who did the steel work), but didn't force Graham to use them. That was Graham's decision. The city had a fixed-price contract with the general contractor, and all subcontracted work should fall within that. If Graham can recoup these increased costs from Augescon, that's up to them.