A C-Train operator that posts on another forum just gave this short-term schedule for 4 car extensions:

Canyon Meadows to start in April and finish before Stampede
Brentwood to start in April and finish before Stampede

Erlton to start after Stampede

Likely no closures of the scale needed at Southland for Canyon Meadows and Brentwood. Should be quick add-ons as the existing platforms don't need to be replaced.
Apparently Sunnyside, Chinook and Anderson to follow with completion in late 2011, early 2012. City Hall will also open in June 2011 and the new 11th Street Station will open in time for West LRT in 2012.

That leaves all of 2013 and most of 2012 to do:

University
Banff Trail
Lion's Park
SAIT

Victoria Park/Stampede
39th Avenue
Heritage
Fish Creek-Lacombe

Victoria Park/Stampede will probably be done after Stampede and before hockey season to not interfere with the traffic from those events. University and SAIT will probably be done between the months of May and August so as to not interfere with the regular post-secondary school year.