The construction will be pretty intensive and quick along the entire route. Some important milestones:

- 29th, 38th, and 39th Streets will be closed permanently on March 1st, 2010.

- 17th Avenue between 40th and 33rd Streets reduced to 2 lanes each way on March 1st, 2010 until Fall 2011.

- Tunnel starts construction in April 2010 near 39th Street

- Elevated guideway construction begins in May 2010 (between 11th Street West and Crowchild Trail)

- Sarcee Trail detour road opens in July 2010 and interchange construction begins.

- Bridges at 42nd Street and 45th Street (over the LRT trench) open in October 2010

- New Ernest Manning High School (west of 69th Street) opens in September 2011, old Ernest Manning High School is knockeed down and tunnel construction continues

http://www.westlrt.ca/contentabout/history.cfm